CDS 2019 OMR Public Consultation – Concluding Report

Background

Connecting Devon and Somerset (CDS) launched their OMR Public Consultation on the 5th of November 2019, the consultation closing for responses on the 10th December 2019.

The consultation focused on the following numbers of Black, Grey, White and Under Review NGA premises, as well as basic broadband coverage.

 

Postcodes Number of Postcodes Number of Black NGA Premises Number of Grey NGA Premises Number of White NGA Premises Number of Under Review Premises Premises Totals
White 14,671 1,495 70,084 95,065 4,930 171,574
Grey 38,452 7,279 570,663 0 0 577,942
Black 12,421 258,379 9,417 0 0 267,796
Under Review 4,243 1,827 62,648 0 18,707 83,182
Total 69,787 268,980 712,812 95,065 23,637 1,100,494

 

CDS sent out emails to 58 companies notifying them about the launch of the consultation and published details on the launch of the consultation on their website at the following link, as well as on the Council News Centre pages: https://connectingdevonandsomerset.co.uk/cds-2019-omr-public-consultation/

Nine companies responded to the consultation, four of which having no comment to make, with five submitting revised data/data clarifications. CDS also received 28 responses from members of the public, the majority providing speed checks correlating with the consultation data. Two responses required a change of records. The first relating to an incorrect premises classification by Ordnance Survey, resulting in the inclusion of an additional white premises to the total premises baseline. The second being the reclassification of 30 premises to under review. No comments were received regarding Basic Broadband coverage.

The result of all public comments and submissions means that the post-consultation NGA intervention area is as follows:

 

Postcodes Number of Postcodes Number of Black NGA Premises Number of Grey NGA Premises Number of White NGA Premises Number of Under Review Premises Premises Totals
White 14,542 2,280 81,937 85,963 8,411 178,591
Grey 39,691 7,364 605,427 0 0 612,791
Black 12,491 258,036 10,112 0 0 268,148
Under Review 3,063 454 21,319 0 19,192 40,965
Total 69,787 268,134 718,795 85,963 27,603 1,100,495

 

Mapping and Postcode Data

The follow map shows the post-consultation NGA white, grey, black and under review postcodes post from the above table:

The following file lists the post-public consultation NGA postcodes making up the above map: nga-postcodes-final

The following file lists the post-public consultation Basic Broadband postcodes making up the above map: basic-postcodes-final

Resulting Procurement Decisions

Lotting and Target NGA White Premises

After extensive engagement with the market, the programme has decided to split the former 5 Gigaclear Lot Areas into 6 lots (as shown in the map below). Each lot contains the following types of premises, based on results of the latest OMR process:

Lot Name Total Premises* Target NGA White Premises Under Review NGA White Premises (potentially in scope of the contract at a future date) Out of Scope Premsies
A 196,762 11,035 5,706 180,021
B 79,549 7,874 2,293 69,382
C 112,561 12,246 1,403 98,912
D 84,594 9,001 1,666 73,927
E 172,543 13,443 9,709 149,391
F 318,283 15,261 12,097 290,925

*as the current new procurement is focused on areas with remaining Phase 2 funding (i.e. the 5 former Gigaclear lot areas), the above totals are lower than those for the whole geographic area (i.e. the tables listed in the Background section of this report).

Timescales

The indicative procurement timescales are set to be as follows:

Activity Date
Issue SQ Documents to Market 20th February 2020
Last Date for Tenderers to submit SQ Questions 5pm on 10th March 2020
Last Date for the Authorities to Answer SQ Questions 5pm on 16th March 2020
Deadline for SQ submission 12.00 noon on 23rd March 2020
Authorities evaluate SQ 23rd March – 27th March 2020
Notification of results of SQ stage. Unsuccessful Tenderers notified of the reasons 30th March 2020
Issue ISIT Documents to Tenderers 30th March 2020
Last Date for Tenderers to submit ISIT Questions 5pm on 26th May 2020
Last Date for the Authorities to Answer ISIT Questions 5pm on 2nd June 2020
Deadline for Initial Tender submission 12.00 noon on 12th June 2020
Authorities evaluate Initial Tenders 15th June – 26th June 2020
Notification of results of ISIT stage. 16th May 2020
Negotiation with selected Tenderers 29th June – 17th July 2020
Negotiation closed. Issue ISFT Documents 21st July 2020
Last Date for Tenderers to submit ISFT Questions 5pm on 5th August 2020
Last Date for the Authorities to Answer ISFT Questions 5pm on 12th August 2020
Deadline for Final Tender submission 12.00 noon on 21st August 2020.
Evaluation of Final Tenders 24th August – 2nd October 2020
Preferred Bidder(s) identified 5th October 2020
Due Diligence 6th October – 23rd October 2020
Standstill notices issued 26th October 2020
Award Contract 16th November 2020

COVID-19 Info